Construction Updates

Cool Timeline

2024
Proof-Roll Day

Proof-Roll day has finally arrived! This is the process of testing the subgrade before gravel and asphalt can be put down for the new roadway.

Demo Work and Storm Sewer Installation

Demo work and installation of the storm sewer continues at the front entrance. Everybody just loves road construction! 🙂

Final Stage of Demolition Marks Key Milestone in Our Subdivision Development

The final stage of demolition has begun at the entrance of the subdivision!

Construction Begins! Neal & Mandy Break Ground on ‘Wonder Nest’

Construction has officially started on the first home at The Ridge on Williams Creek! Neal and Mandy celebrated the groundbreaking of their new home, affectionately named ‘Wonder Nest.’ The couple even designed a custom shovel featuring their house logo, with Wonder Bread dots representing eggs in a nest.

Stay tuned for more exciting updates as construction progresses!

Sanitary Sewer Connection to City’s Lift Station Completed

June 13th – “Our sanitary sewer is tied into the city’s lift station. Now we have to wait for 30 days while the city conducts a mandatory pressure test, as apparently contaminating the Indianapolis water supply would be “bad”.

Boring Machine Forcing the New Sewer Line into the Ground

5/21/2024 – Equipment Arrives for the Sanitary Sewer This Morning

We Have Passed Our 3rd Pre-Construction Meeting with the City Inspectors, and Are Given the Go-Ahead to Proceed with Installation.

5/17/2024 – Work Begins on the Storm Sewer on the Other Side of the Bridge Today

Work Continues on Storm Sewers

Work continues on, and concrete arrives for the storm sewers. 🏗️🌧️

Major Storm-Water Drainage Pipes Construction Begins 🌧️🛠️

Construction begins on one of three major storm-water drainage pipes.

Dirt Work on East Side of Bridge🌉🚧

Initial dirt-work begins on the east side of the bridge.

Dirt work begins on the east side of the bridge.
Initial dirt-work begins on the east side of the bridge.

Late-Night Retrieval🌙🚚

Late-night retrieval.

Citizens Energy Group van during late-night retrieval operations.
Citizens Energy Group van during late-night retrieval operations.

Widening of Forgotten Creek Drive 🛤️

Widening of Forgotten Creek Drive continues.

Continued Dirt Work 🚜

Dirt work continues on the old road (now completely removed) and the new swale alongside of it.

Dirt work on the old road at The Ridge on Williams Creek.
Dirt work continues on the old road (now completely removed) and the new swale alongside of it.

Concrete Structures Arrive 🧱

Concrete structures arrive for installation of the new storm drains.

Original Roadway Removed 🚧

No turning back (literally) now, as the original roadway is removed from existence.

Dirt work on the old road at The Ridge on Williams Creek.
Dirt work continues on the old road (now completely removed) and the new swale alongside of it.

New Power Grid Work Begins⚡

A.E.S. begins work on the new power grid.

April Showers Bring Caterpillars 🌧️🐛

April showers bring May flowers.. and in our case, they also bring Caterpillars! Dirt-work finally begins with the bio-retention pond.

Pre-construction Meeting Completed

✅ Pre-construction meeting completed this morning, and the final permits have been issued! We are released for construction!!

Infrastructure and Environmental Preparations Underway at The Ridge: Power Pole Installation and Silt-Fence Implementation

The City of Carmel, Public Works begins installation of new power poles on 96th Street to allow room for our new traffic blister and turning lane.

Update from March 21st, 2024, showcasing the initiation of new power pole installations on 96th Street by the City of Carmel Public Works.
Progress on March 21st, 2024: The City of Carmel Public Works team commences the installation of new power poles, facilitating the construction of a traffic blister and a turning lane.

Trenching for, and installing silt-fence in preparation for starting construction on the our new roadway and installing utilities.

Permitting Milestone Achieved for The Ridge on Williams Creek

February 27th, 2024 – After 7 Months of Work, The Final Approval for Permitting!

Screenshot of an email confirming the final approval for construction permits dated February 27th, 2024, with sensitive contact information redacted.
Official confirmation received on February 27th, 2024, marking the culmination of seven months of diligent work leading to final permit approval for The Ridge on Williams Creek construction project.

2023
Celebrating the Milestone of the Secondary Plat Recording

After what seems like years, (wait, it actually has been years) we were finally able to record our Secondary Plat with the City of Indianapolis!

Bridge Railing Installation

Installed 10 sections of steel railing today, each one weighing in at a little over 1,000lbs.

Bridge Installation Timelapse

All of this work, just to get from here, to there!

2022
Brrrr…. Parapets get poured

Despite the cold today, concrete for the parapets gets poured this morning.

Deck Forms Removed

Deck forms are removed, and work begins on the parapets.

Concrete is delivered

Concrete is delivered for the new bridge deck!

Forms, Rebar, & Drains

Forms, rebar, and drains are set in place for the new bridge deck.

Forms, rebar, and drains are set in place for the new bridge deck.

Back-Filling the Cured Grout + Satisfaction

After the grout has had time to cure, back-filling work begins. Layers of sand and #53 stone are compacted 8” at a time.

A truly satisfying feeling!

 

Building Bridges: Securing Sections with Bolts and Drilling 1″ Holes

After the grout sets, 1” holes are hammer-drilled and plates are bolted in to tie the bridge sections together.

 

 

Building a Bridge at The Ridge on Williams Creek

The steps include setting the first and second sections into place, placing the third section and the head walls, and sealing and grouting the sections and foundations together. Finally, the workers took a break for a beer after completing the hard work.

“First bridge section being set into place.”

“Section #2 going in.”

“Third section, and then the head-walls. Each section weighs 18 tons, the head walls are 7 tons apiece.”

“Sealing and grouting the sections together, and to the foundations.”

“Whew, time for a beer.”

 

Construction of New Bridge Begins with Arrival of Crane and Set-up

The crane is here!  Set-up begins.

The bridge sections begin to arrive, and are staged at a closed restaurant just down the street.

A quick stop on 96th Street with the police providing traffic control, then a long reverse 1,000’ down the road to the crane.

New rock is delivered in anticipation of the crane and bridge arrival.

A large pile of new rock is ready to be used in the construction of the bridge. The rock is placed in a large open area, surrounded by some trees and shrubs. The sky is bright and clear, & the construction process is about to begin. The new rock glitters in the sunlight, hinting at the bright future ahead for this project.

“Hey, I think that truck bed may be a little too high…”

 

Creating The Bridge Foundations

29 yards of concrete going in today to create the foundations for the bridge. Very Exciting Day!

Rebar

Rebar is being set for the bridge foundations.

Exciting Day!

Ground Breaking!! Excavation for the bridge foundations has begun; the first official bucket full of dirt.

The final result, two 10’ deep holes.

Widening The Original Gravel Road

Fall is upon us and as the day for actual construction nears, I have to widen the original gravel road some to allow for the bridge delivery trucks!

Field Trip!
Tom Kretz - Next to Concrete Bridge

 Where I visit the manufacturing facility and inspect the first piece of our cast concrete bridge today (it’s huge!) and get an inside look at the prep work for section #2.  Special thanks to John Barth and Chris Bettum at Contech Engineered Solutions, in Dayton, Ohio.

2021
Our “Coming Soon” sign for the front entrance arrived today, just before the lightning storm.

Landscaping in 95 degree heat might be a little safer, but isn’t much better.

2020
Next up for clearing is the area next to Williams Creek

Next up for clearing is the area next to Williams Creek, which hasn’t been touched in years and must also be cleared by hand, so says IDNR!

We are going to need a name

Well, it’s a Ridge, on Williams Creek.

Who are you?

Getting introduced to some of the current residents.

Research!

A little digging reveals the property’s original owner as Alexander Taggart, who brought the original log cabin (still standing today) to the property around 1903, develops Wonder Bread in 1921, and then builds their family home there in 1939. A guest house, which is also still standing, would follow in the 50’s.

1st Visit

Me: (jokingly) “My builder friend Brad thinks I should develop my own subdivision.”

Paul: (my realtor) “Have you seen the 12 acres for sale on 96th Street?”

Me: “I didn’t think there was any land left in Marion County?”

Paul: “It’s been for sale for years. It’s on Williams Creek.”

Me: “What?”

Paul: “You busy? Lets take a drive over there.”

My wife Jackie: (later that evening) “You want to do what??”